Ready to go — but what does Palma's second ring road really mean for Coll d'en Rabassa?

Timeline and costs for Palma’s second ring road

Overview of start date, two construction phases, and the €350 million budget for the Palma ring road near Coll d'en Rabassa.

Published: September 16, 2026
Ready to go — but what does Palma's second ring road really mean for Coll d'en Rabassa?

Answer

When is Palma's second ring road expected to start, and how long will construction take?

Excavators are expected to roll in by the end of 2026. The project totals around €350 million in two phases: Phase 1 about two years and eight months, Phase 2 a little over three years, including a roughly one-kilometre tunnel under Coll d'en Rabassa.